M2001077 Piceance Pit IHC Scott, Inc. Transfer from IHC Scott, Inc. to W.W.Clyde & Co. NULL NULL SO 5 3/18/2024 NULL NULL NULL NULL NULL
M2008070 White River Pit OWL SWD Operating, LLC TEMPORARY CESSATION NOTICENULL No industry activity or economic justification.NULL TC 1 4/2/2024 NULL NULL NULL NULL NULL
M2021052 Rifle Gravel Pit #1 IHC Scott, Inc. Transfer from IHC Scott, Inc. to W.W. Clyde & Co. NULL NULL SO 1 4/8/2024 NULL NULL NULL NULL NULL
M2012023 Shot Rock Pit Tamrock Gravel LLC Amendment submitted as a result of a Board Order to include off-site affected areas.NULL This Amendment is the result of a MLRB Board Order that instructs the Operator to add areas that have been affected off-site into the permit boundary. This amendment has been submitted as a 'reclamation only' revision.NULL AM 1 3/25/2024 4/2/2024 NULL 7/1/2024 NULL NULL
M2012023 Shot Rock Pit Tamrock Gravel LLC Surety ReductionNULL Surety Reduction to account for the recent reclamation conducted on-site.NULL SR 1 2/26/2024 3/4/2024 3/19/2024 5/3/2024 NULL NULL
M2007007 Mooney Hills Permit All-Rite Paving & Redi-Mix, Inc. Surety Release Mooney Hills Permit M2007007NULL All Rite Paving and Redi Mix would like to request the full release of this site, including the surety. The amendment for the adjoining permit, Mooney 5804 Altura Pit (Permit No. M-2010-012), now encompasses this site. As the two sites are now permitted as one (M-2010-012), Permit No. M-2007-007 can be fully released. NULL SL 1 3/18/2024 4/11/2024 NULL NULL NULL NULL
C1981012 New Elk Mine New Elk Coal Company, LLC Permit Renewal Application No. 8 (RN8)NULL New Elk Coal Company is requesting to renew permit C-1981-012 for another five year permit term. NULL RN 8 8/28/2023 8/31/2023 NULL 12/29/2023 3/29/2024 NULL
M2023005 Lascar Pit Siete, Inc. Technical Revision NULL NULL TR 1 4/14/2023 4/17/2023 NULL 5/17/2023 5/2/2023 NULL
M2022004 Section 20 Mine Jalisco International, Inc. Full/Final Release NULL NULL SL 1 4/22/2024 NULL NULL NULL NULL NULL
M1977342 Henderson Mine Climax Molybdenum Company CDPHE Complaint forwarded to DRMS NULL Caller reported to CDPHE observing white crystalline material blowing onto the tailings pond and the river,NULL CT 1 5/26/2022 5/26/2022 NULL NULL NULL NULL
M2004051 Wattenberg Lakes Holcim - WCR, Inc. Request to increase the affected land boundary from 245.0 to 251.2 acres, an increase of 6.2 acres.NULL Amendment Application to increase the affected land boundary from 245.0 to 251.2 acres, an increase of 6.2 acres and reconfigure the final reservoir design by combining Pond 1 and Pond 2 into one (1) reservoir.NULL AM 1 5/11/2023 6/15/2023 8/2/2023 9/13/2023 6/14/2024 NULL
M2001107 NCCI Pit #1 Northern Colorado Constructors, Inc. Aggregate Div Acreage ReductionNULL NCC is requesting an acreage release of the water storage cell. The compacted clay liner was approved by the Division of Water Resources on November 30, 2023.NULL AR 1 3/5/2024 3/11/2024 NULL 5/10/2024 NULL NULL
M2008009 Lyster Pit Oldcastle SW Group, Inc. dba United Companies Acrage reduction request of 37.1 acres.NULL Acrage reduction request of 37.1 acres.NULL AR 1 7/27/2020 8/5/2020 NULL 10/5/2020 NULL NULL
M1994081 Peat Mine Ronald L Barrier Transfer from Ronald L. Barrier to Mortensen's Landscape & Irrigation LLCNULL NULL SO 2 3/13/2024 NULL NULL NULL NULL NULL
M1979142 West of Maybell Pit Colorado Department of Transportation NULL NULL SL 1 8/24/2021 NULL NULL NULL NULL NULL
C1980004 McClane Canyon Mine ARC McClane Canyon, LLC Midterm Review Findings Dated NULL Midterm Review No. 9NULL MT 9 12/22/2023 12/22/2023 NULL NULL NULL NULL
C1981008 New Horizon Mine Elk Ridge Mining and Reclamation, LLC Phase I Bond ReleaseNULL Elk Ridge Mining and Reclamation, LLC is requesting Phase I Bond Release for 85.5 acres that were backfilled and graded, including topsoil replacement and seeding, in 2023. The acreage requested for bond release is located in the southern part of Section 36, just north of BB Road. NULL SL 27 1/15/2024 2/21/2024 2/16/2024 5/5/2024 NULL NULL
C1981008 New Horizon Mine Elk Ridge Mining and Reclamation, LLC Phase 1, II and III Bond ReleaseNULL Elk Ridge Mining and Reclamation LLC is submitting an application for Phase I, II, and III performance bond release for five backfill monitor monitoring wells and seven exploratory drill holes.NULL SL 28 2/29/2024 4/1/2024 4/5/2024 NULL NULL NULL
C2010089 New Horizon North Mine Elk Ridge Mining and Reclamation, LLC Phase I, II, and !!! Bond ReleaseNULL Elk ridge Mining and Reclamation, LLC is requesting Phase I bond release on 34 acres of reclaimed sediment control structures. Phase I, Phase II and Phase III bond release requests were also made for 1.2 acres associated with an access road and discharge piping that routes water from AA road and are permitted to remain as permanaent structures to support the current post-mining land use.NULL SL 4 1/11/2024 2/13/2024 2/9/2024 5/5/2024 NULL NULL
C2010089 New Horizon North Mine Elk Ridge Mining and Reclamation, LLC TR-25NULL Elk Ridge Mining and Reclamation, LLC submitted a Techniacal Revision, TR-25, to incorperate the as-built for the Garvey and Company Pond 1 into the permit.NULL TR 25 4/3/2024 4/11/2024 NULL 4/11/2024 NULL NULL
M2009079 Peroulis Brothers Snake River Pit Precision Excavating, Inc. Request for Surety ReductionNULL Precision Excavating, Inc proposes a surety reduction for the Peroulis Brothers Snake River Pit to reduce the bond for the site to the amount required to complete the seeding of vegetation.NULL SR 1 10/27/2020 11/6/2020 NULL 1/5/2021 NULL NULL
C1996084 Lorencito Canyon Mine New Elk Coal Company, LLC 2020 Midterm ReviewNULL NULL MT 5 5/5/2020 5/5/2020 NULL NULL NULL NULL
M1996013 Hasty Pit Carder, Inc. NULL NULL CS 2 1/28/2020 NULL NULL NULL NULL NULL
M1995057 Rudibaugh Pit Deb Rudibaugh Forfeit FW MV-2021-002NULL NULL CS 3 10/20/2021 10/22/2021 NULL NULL NULL NULL
M1992054 Ignacio Pit LBCR, LLC Surety ReductionNULL Surety ReductionNULL SR 1 3/12/2024 3/13/2024 NULL 5/13/2024 NULL NULL
M1983159 Gleason Pit Glacier Ridge Aggregates Corp. Transfer from S & S Aggreagtes Inc to Glacier Ridge Aggregates Corp.NULL NULL SO 3 4/4/2024 NULL NULL NULL NULL NULL
M1984014 C-JD-8 Highbury Resources Inc. NULL NULL TC 3 4/1/2019 NULL NULL NULL NULL NULL
M1986076 Incas Mine Mayday Livery LLC NULL Final reclamation has been completed. The operator is requesting release from further reclamation responsibility.NULL SL 1 1/23/2024 1/23/2024 NULL 3/25/2024 NULL NULL
M2008083 Black Cloud Mine Resurrection Mining Company Complaint from Brian Werderman - downstream property owner: Blown out beaver dams, sedimentationNULL NULL CT 1 7/8/2019 NULL NULL NULL NULL NULL
M1977493 Climax Mine Climax Molybdenum Company Updates to the Exhibits E, F, G & I for the associated 2024 reclamation cost updates submittal.NULL Provide updates to Exhibit E: Reclamation Plan, Exhibit F Reclamation Plan Maps, Exhibit G Water Information and Exhibit I Soil Information.) Information is to aid with the 2024 reclamation cost update.NULL TR 37 3/29/2024 4/9/2024 NULL 4/28/2024 NULL NULL
M1977305 C-LP-21 Mine Highbury Resources Inc. End TC to Reclamation StatusNULL NULL CS 1 2/3/2020 6/23/2021 NULL NULL NULL NULL
M2021058 Arkansas Valley Slag (AVS) CJK Milling Company, LLC Request for Technical RevisionNULL NULL TR 1 4/11/2022 NULL NULL NULL NULL NULL
M2023033 Ewing Gravel Pit BURNCO Colorado, LLC Technical RevisionNULL NULL TR 1 4/16/2024 NULL NULL NULL NULL NULL
M1987116 Siskin Colorado Quarries Inc 110c to 112c Conversion ApplicationNULL 110c to 112c Conversion ApplicationNULL CN 1 2/6/2024 2/20/2024 4/24/2024 5/20/2024 NULL NULL
M2009010 Stewart Pit II McCormick Excavation & Paving, LLC Full/Final Release of Entire Permitted AreaNULL Full/Final Release of Entire Permitted AreaNULL SL 1 2/22/2024 2/22/2024 NULL NULL NULL NULL
M2006047 Klassen Pit Kit Carson County Full/Final Release of Entire Permitted AreaNULL Full/Final Release of Entire Permitted AreaNULL SL 1 2/26/2024 2/26/2024 NULL NULL NULL NULL
M1991080 Van Egmond Stone Pit Russell Van Egmond 110c to 112c Conversion Application CN1: Addition of 10 acres to the permit for a total of 20 acres.NULL 110c to 112c Conversion Application CN1: Addition of 10 acres to the permit for a total of 20 acres.NULL CN 1 3/23/2022 12/29/2022 NULL 3/29/2023 9/26/2023 NULL
M1980244 Cresson Project Cripple Creek & Victor Gold Mining Company Citizen Complaint from Carl J PochNULL Citizen Complaint from Carl J PochNULL CT 5 4/8/2023 4/8/2023 NULL NULL NULL NULL
M1980244 Cresson Project Cripple Creek & Victor Gold Mining Company Closure stormwater design updatesNULL Newmont Corporation’s Cripple Creek and Victor Gold Mining Company (CC&V) hereby provides Technical Revision (TR) 131 documenting updated closure stormwater designs; as committed to during the second and third adequacy reviews of the CC&V Amendment 13 (AM-13).NULL TR 131 3/24/2022 3/24/2022 NULL 4/25/2022 5/15/2023 NULL
M2018007 Project P.J. Taylor Conway Acreage Reduction to remove Mining Area #3 to account for the acreage of the AM1 access road.NULL Acreage Reduction Description: Removal of Mining Area #3 to account for the acreage of the AM1 access road. Please note, no mining activities have occurred in Mining Area #3 under M-2018-007.NULL AR 1 11/15/2021 12/2/2021 NULL 1/31/2022 5/31/2022 NULL
M2013006 Taylor Pit Bower Brothers Construction, Inc. FULL RELEASE OF PERMITED AREA - TAYLOR PIT, absorbed by Hertzog pitNULL Full Release of Permitted Area Taylor Pit - M2013006 in Moffat County. Now Known as The Hertzog Pit. NULL SL 2 4/8/2024 4/8/2024 NULL NULL NULL NULL
M2020023 Langston Borrow Pit Langston Concrete, Inc. Mining without a permitNULL NULL CT 1 4/22/2020 4/24/2020 NULL NULL NULL NULL
M2020028 Big Johnson Reservoir Fountain Mutual Irrigation Company The excavation site is 5550 Goldfield Rd. Colorado Springs, 80911, and the material is being transported for site improvements to 3700 Drennan Rd. Colorado Springs, 80910NULL They have started the project we spoke about last week and have a fleet of trucks hauling. As you can see, this is a substantial amount and it's also apparent they have been doing this before if you see how far back to the right hand side of the photo the excavation goes. Please address as soon as possible. The excavation site is 5550 Goldfield Rd. Colorado Springs, 80911, and the material is being transported for site improvements to 3700 Drennan Rd. Colorado Springs, 80910 NULL CT 1 5/6/2020 5/6/2020 NULL NULL NULL NULL
M1980244 Cresson Project Cripple Creek & Victor Gold Mining Company TR142 - South Cresson BackfillNULL This Technical Revision is for the backfilling of the South Cresson Pit.NULL TR 142 3/13/2024 3/13/2024 NULL 4/12/2024 5/10/2024 NULL
M1980249 Houchin Gravel Pit Charles W Houchin Transfer from Charles W. Houchin to Houchin Inc NULL Transfer of the Houchin Gravel Pit from Charles W. Houchin to Houchin Inc. NULL SO 1 2/22/2024 NULL NULL NULL 6/1/2024 NULL
M1977210 Snyder Quarry City of Colorado Springs Noticed this morning and continuing into this afternoon that there is an EXTREME amount of trucks carrying aggregate out of the Snyder Quarry. In 19 minutes I videoed 12 loaded trucks departing the quarry.NULL NULL CT 1 4/22/2020 4/22/2020 NULL NULL NULL NULL
C1982056 Foidel Creek Mine Twentymile Coal, LLC MR325-6East & WC Mains Utility Borehole LocationsNULL 6East Borehole and pad location. WC Mains Utility Borehole and Pad locationNULL MR 325 4/4/2024 4/11/2024 NULL 4/21/2024 4/26/2024 NULL
M1995095 Simla Highway Pit Hill Top Gravel LLC Conversion to 112cNULL Conversion of the existing 110 permit to a 112c operation.NULL CN 1 3/4/2024 3/11/2024 4/24/2024 6/10/2024 NULL NULL
M2002020 25th Avenue Site City of Greeley Cache la Poudre River Bank StabilizationNULL Past high-flow events also scoured the Cache la Poudre embankment adjacent to the 25th Avenue Site Pond A reservoir. The bank stabilization project will install protection measures to reduce or eliminate erosion at that location. These measures will protect the existing 25th Avenue Site facilities.NULL TR 3 9/28/2023 9/28/2023 NULL 10/30/2023 4/26/2024 NULL
M2002096 Ranch Land Rock Pit #1 Holcim (US) Inc. Permit and Bond Release for Permit M-2002-096NULL With the approval of Portland Limestone Quarries M-1977-344 AM-02 on March 14, 2024, the above referenced permit is included within the permit boundary of AM-02 as Red Creek Quarry.NULL SL 1 4/2/2024 4/15/2024 NULL NULL NULL NULL
M2002004 Pueblo Cement Plant and Limestone Quarry GCC Rio Grande, Inc. Coal Reject Material and Update Reclamation CostsNULL GCC is requesting to beneficially reuse coal reject materials generated from the cement plant's coal mill as backfill in the quarry. Additionally, GCC is requesting to update the reclamation costs based off recent discussions with DRMS.NULL TR 13 3/28/2024 NULL NULL NULL 6/26/2024 NULL
M1998038 Two Rivers Fremont Paving & Redi-Mix, Inc. Adds approximately 18.2 acres, updates mining and reclamation plans, and addresses issues identified from Feb 2023 inspection.NULL This amendment adds approximately 18.2 acres, updates mining and reclamation plans to adhere to the Division's requirements, and addresses issues identified as a result of the inspection performed in February 2023.NULL AM 1 1/22/2024 2/8/2024 3/28/2024 5/8/2024 NULL NULL
M2010043 Falk Pit #1 Chamberlain Concrete Conversion, 9.9 acres to 11.9 acres permittedNULL Conversion from 110c to a 112c operation to include areas that were affected outside permit boundary, submitted in compliance with Board Order and Notice of Violation No. MV-2023-019. NULL CN 1 3/11/2024 NULL NULL NULL NULL NULL
M2008076 Robinson Sons Gravel Pit No. 1 Robinson Sons Inc David Vigil complaint regarding inadequate structure agreement. NULL NULL CT 2 2/13/2019 NULL NULL NULL NULL NULL
M2003002 Ghost River Gravel Pit HCR High Country Repair Surety incrrease to cover the cost of reclamation at the site.NULL NULL SI 2 8/26/2021 8/26/2021 NULL 10/25/2021 1/15/2022 NULL
M1989056 Timnath Pit McAtee Construction Company Monitoring Well Technical RevisionNULL Post DNRS site inspection, update to groundwater monitoring planNULL TR 1 2/28/2024 2/28/2024 NULL 3/29/2024 4/28/2024 NULL
M1986123 Kirtright Pit Coulson Excavating Company, Inc. Kirtright Pit AmendmentNULL Amendment application to expand permit area to the north.NULL AM 1 2/27/2024 NULL NULL NULL NULL NULL
M1977410 Cross Gold Mine Grand Island Resources LLC NULL NULL CT 5 6/30/2023 NULL NULL NULL NULL NULL
M1977439 Home Office Mine Martin Marietta Materials, Inc. Hydraulic Evaluation of E-I and E-IINULL Per Comment 39 of Amendment 04, we agreed to complete an evaluation on Ponds E1 and E2 for a 100-year flood event. Based on the conclusion and recommendations on Page 5, no changes are needed to the reclamation plan.NULL TR 7 1/16/2024 1/16/2024 NULL 2/15/2024 5/15/2024 NULL
M1980244 Cresson Project Cripple Creek & Victor Gold Mining Company Proposed Numeric Protection LevelsNULL Proposal for Numeric Protection levelsNULL TR 136 3/30/2023 3/30/2023 NULL 5/1/2023 11/30/2023 NULL
M2017036 Knox Pit Loveland Ready-Mix Concrete, Inc. Groundwater-Sampling Reduction RequestNULL LRM is seeking a reduction in the frequency of water quality sampling. There is now over 5 years of data that has been taken quarterly and a solid baseline has been established.NULL TR 2 2/2/2024 2/2/2024 NULL 3/4/2024 5/2/2024 NULL
M1983112 Murdock Gravel Pit Kiowa County Full/Final ReleaseNULL A Full/Final Release has been requested.NULL SL 2 4/8/2024 4/10/2024 NULL NULL NULL NULL
M1993059 Midwestern Farms Midwestern Farms Full/Final ReleaseNULL A Full Release Requst has been submitted for Midwestern Farms.NULL SL 1 2/29/2024 3/13/2024 NULL 5/13/2024 NULL NULL
C1980007 West Elk Mine Mountain Coal Company, LLC Partial Phase III Bond ReleaseNULL SL-17 seeks Phase III Bond Release on 9.25 acres of pads and roads associated with Mine Ventilation Boreholes (MVBs) and exploration holes situated in the West Bench, Sylvester Gulch, Shaft Canyon Road and Saddle Road areas. Reclamation work on the SL-17 parcels was completed between 2004 and 2008. NULL SL 17 11/8/2022 12/19/2022 1/6/2023 8/26/2023 NULL NULL
C1980007 West Elk Mine Mountain Coal Company, LLC TR-153 - B to E Seam Vent ShaftNULL With TR-153, Mountain Coal Company seeks to permit a concrete drill pad with a 19” pilot hole at the existing Deer Creek Vent Shaft facility. The pilot hole will allow for the construction of a raised bore vent shaft from the B-Seam to the E-seam.NULL TR 153 4/8/2024 4/12/2024 4/28/2024 6/11/2024 NULL NULL
M1977170 Butala Gravel Pit Butala Construction Company Permit Amendment Application (AM-2)NULL Application to amend permit pursuant to June 15, 2023 Settlement Agreement between Butala Construction Company and DRMS. This Amendment will update the Mining and Reclamation plans, no additional acreage is being requested. NULL AM 2 11/20/2023 2/5/2024 NULL 5/6/2024 6/6/2024 NULL
M1990057 Leadville Mill Union Milling Company, LLC Conversion to 112(d)NULL This Amendment proposes Cyanide Tank Leach Leach recovery for precious metals, additional surface disturbance, and a new Filtered Tailings Storage Facility. Also proposed are significant updates to the site, and the permit including the Environmental Protection Plan. NULL CN 3 2/2/2024 2/8/2024 NULL 5/8/2024 7/10/2024 NULL
M2004045 Hanna Pit No. 1 Rio Grande Ranch, LLC Board Ordered Surety Forfeiture, 3/18/2022NULL NULL SF 1 4/13/2022 4/13/2022 NULL NULL NULL NULL
M2020008 Rifle Gravel Pit #1 Scott Contracting, Inc. NULL NULL AM 1 2/3/2021 NULL NULL NULL NULL NULL
M1977300 Schwartzwalder Mine Colorado Legacy Land, LLC Technical Revision NULL NULL TR 31 8/24/2023 NULL NULL NULL NULL NULL
M1978052 Howe Pit City & County of Denver, Board of Water Commissioners Infrastructure Map RevisionNULL Map revisions to show all existing infrastructure and future infrastructure projects.NULL TR 2 4/19/2024 NULL NULL NULL NULL NULL
M1979195 Road Runner Rest Denver Water Department Mining Permit Infrastructure RevisionNULL Map revisions to show all existing infrastructure and future infrastructure projects.NULL TR 8 4/19/2024 NULL NULL NULL NULL NULL
M1980110 Henderson Development E-470 Public Highway Authority Addressing 5 items requested by the Division including perimeter drain as-builts, pit elevation survey data, groundwater monitoring data and plan, groundwater report from BBA, and potential mitigation measures.NULL Addressing 5 items requested by the Division including perimeter drain as-builts, pit elevation survey data, groundwater monitoring data and plan, groundwater report from BBA, and potential mitigation measures.NULL TR 6 3/28/2024 3/28/2024 NULL 4/27/2024 NULL NULL
M1977153 Reclamation Pit No 1 Denver Water Department Infrastructure RevisionsNULL Map revisions to show all existing infrastructure and future infrastructure projects.NULL TR 2 4/19/2024 NULL NULL NULL NULL NULL
M1999034 Cooley Reservoir & Fulton Wildlife Area Holcim - WCR, Inc. Revised Reclamation Plan Map, SEO Liner Recertification, Flood Control Mitigation Plan and As-Built DrawingsNULL Updates to Reclamation Plan Map to show 2015 flood repairs, submittal of 2020 SEO liner recertification, Flood Control Mitigation Plan and As-Built DrawingsNULL TR 7 4/3/2024 4/4/2024 NULL 5/3/2024 NULL NULL
M2000016 Riverbend Operation Martin Marietta Materials, Inc. Citizen ComplaintNULL 11573 County Road 6, Fort Lupton CO South half of section 24 township 1 North Range 67 West The de-watering of the Rittenhaus and Norden gravel pits has dried up the water well to my house. These pits are part of the Riverbend project of Martin Marietta. I have four water wells on my farm and I'm afraid that they will all dry up as a result of this mining operation. George Stieber 11573 County Road 6 Fort Lupton, CO 80621 g.william.stieber@gmail.com 303-659-7805NULL CT 2 3/27/2023 NULL NULL NULL NULL NULL
M2022006 Motorcross Borrow Pit SEMA Construction, Inc. Citizen ComplaintNULL Kevin McCarty, 2275 Alpine Sky Drive, Berthoud, CO 80513, kevin@mccartylw.com, 970-581-1953. 3/4 mile south of Hwy 56 on the east side of WCR 7 & on west side of I-25. East of Berthoud, CO My understanding is that this permit is specifically for construction of I-25. We have noticed trucks heading south and when we followed them, we discovered fill dirt was being supplied to a Mead development. This limited permit was approved without any notice or input from adjoining landowners and we are told it was approved in this manner because of the limitation in time and use for the I-25 project. An expansion of use beyond that does not seem appropriate. We discussed the original use with SEMA operator when the project started. While we don't agree with embarking on a project of this scale with no county approval and no ability for public input, we have decided not to pursue further actions regarding the use of this pit specifically for I-25. However, an expansion of use beyond that is another story.NULL CT 1 1/19/2023 NULL NULL NULL NULL NULL
C1981010 Trapper Mine Trapper Mining, Inc. Phase I Bond Release NULL A Phase I bond release on 316.5 acres in D/E and I Pits reclaimed from 2008 through 2023.NULL SL 25 12/18/2023 12/22/2023 9/3/2023 NULL NULL NULL
C1981010 Trapper Mine Trapper Mining, Inc. L-Pit (K Knob) Extension and East J-Pit Dragline CNULL Revision to add additional mining in the southeast portion of the L-Pit, commonly referred to as K Knob. The pit will be extended to the north. Additionally revised materials are included for a proposed J-East pit that will consist of five surface dragline cuts. The request comprises 50.8 acres oNULL TR 135 2/28/2024 3/8/2024 3/30/2024 5/7/2024 NULL NULL
C1981010 Trapper Mine Trapper Mining, Inc. 2023 Annual Reclamation ReportNULL 2023 Trapper Mine Annual Reclamation ReportNULL TR 136 3/14/2024 3/25/2024 4/20/2024 5/24/2024 NULL NULL
M1979189 Superior S&G Pit City of Aurora Full/Final ReleaseNULL Full bond release of the site for completed reclamation.NULL SL 1 4/13/2023 4/24/2023 NULL 6/23/2023 NULL NULL
M1978051 Gaede Pit Lincoln County Technical Revision TR-5NULL This permitting action was withdrawn on 26 August 2022 and the withdrawal was approved.NULL TR 5 8/22/2022 NULL NULL NULL NULL NULL
M2022009 Monarch DENM Mine Monarch Mountain Minerals and Aggregates, LLC Revision to Groundwater Monitoring and Mitigation PlanNULL This technical revision updates the Groundwater Monitoring and Mitigation Plan to include a baseline water quality analysis. It also includes groundwater monitoring data and results of a groundwater model. NULL TR 1 3/21/2024 3/21/2024 NULL 4/22/2024 5/17/2024 NULL
M2015033 Parcel 122 - Resource Development Project Raptor Materials LLC Revised Acreage and Life of MineNULL Reduction of Permit Boundary by 0.92 acres, inclusion of mineral reserve area into the excavation area, adding plugged and abandoned oil wells to extraction area and extending conveyor.NULL TR 3 4/10/2024 4/10/2024 NULL 5/10/2024 NULL NULL
M2019054 Skull Creek Uinta Mining, LLC NULL NULL AM 1 12/30/2019 1/15/2020 NULL 4/14/2020 8/1/2020 NULL
M1995060 Butcher Pit Southway Construction Company, Inc. NULL NULL TC 2 6/13/2019 NULL NULL NULL NULL NULL
M1987013 Burton Pit Southway Construction Company, Inc. NULL increase FW to 52,786.00NULL SI 2 3/9/2020 3/9/2020 NULL 5/8/2020 NULL NULL
M2001001 Line Camp Pit Stone Sand & Gravel, LLC Transfer from Stone Sand & Gravel to Smith's Materials, LLC NULL NULL SO 3 3/11/2024 NULL NULL NULL NULL NULL
M1990134 Ross Pit James H & Kathleen H Ross Full/Final ReleaseNULL SL-1 is proposing full and final release of the entire permitted area.NULL SL 1 1/12/2024 1/22/2024 NULL 3/22/2024 NULL NULL
M2009079 Peroulis Brothers Snake River Pit Precision Excavating, Inc. Full/Final Release RequestNULL Full/Final Release RequestNULL SL 2 12/18/2023 12/21/2023 NULL 2/19/2024 NULL NULL
C1981019 Colowyo Coal Mine Colowyo Coal Company L.P. Midterm Review Findings Dated May 5,2020NULL NULL MT 8 5/5/2020 NULL NULL NULL NULL NULL
C1984065 Coal Ridge No. 1 Mine C.B. Minerals Company, LLC Midterm Review Findings Dated April 2, 2019NULL NULL MT 8 4/2/2019 NULL NULL NULL NULL NULL